How a project runs, start to finish

If you haven’t hired traffic control before, the sequence isn’t obvious — and getting it out of order is what causes delays. Here is what actually happens.

01Stage

Scope

That’s usually enough to tell you whether a traffic management plan will be required, roughly what crew size the job needs, and whether the municipality is likely to impose restricted hours.

What we need from you: The road, the dates, the shift pattern, and what you’re doing to the road.

Timing: Same or next business day.

02Stage

Plan

A site-specific plan drawn to TMM 2020: device placement, taper lengths for the posted speed, pedestrian and cyclist provision, phasing where the work changes shape. Municipalities reject template plans — Surrey specifically requires plans to be site, segment or phase specific with site-specific drawings.

What we need from you: Site drawings if you have them, the work sequence, and any constraints you already know about — a business that must keep its access, a transit stop, a school zone.

03Stage

Permit

The plan is submitted to the authority that governs that road. Municipal roads go to the city; provincial highways go to MoTI. The names differ — Surrey issues a Traffic Obstruction Permit, Vancouver a Street Use Permit.

What we need from you: Applicant details and timeline confirmation.

Timing: Roughly three to seven business days for municipal processing, from a complete application. An incomplete one doesn’t get rejected quickly; it waits.

04Stage

Mobilise

Crew and equipment scheduled and confirmed. The crew is briefed off the accepted plan — the same document the city signed off.

What we need from you: Confirmed start, site access details, and a contact who will be there.

05Stage

Operate

Setup verified against the plan before work starts, then traffic controlled for the duration. Devices get struck, moved and stolen — they’re monitored and reinstated. If site conditions change enough that the plan no longer fits, we stop, tell you, and revise rather than improvise.

What we need from you: Notice of changes to the work.

06Stage

Demobilise

Devices recovered, road returned to normal configuration, documentation returned to you — for your project file, and for the municipality if the permit conditions require it.

07Programme risk

Build the permit into your programme

The most common cause of a delayed start we see is a permit applied for the week the work was meant to begin.

What we need from you

Exhibit 01What each stage needs from you
StageFrom you
ScopeRoad, dates, shift, scope of work
PlanDrawings, sequence, known constraints
PermitApplicant details, timeline confirmation
MobiliseConfirmed start, access, site contact
OperateNotice of changes to the work

What you can expect from us

  • A quote that reflects the actual scope, not a placeholder to be revised later
  • A plan drawn for your site, not a template
  • Certified crew, currently certified
  • A supervisor who answers the phone
  • Documentation without having to ask twice

Tell us about the project.

Site location, start date, duration and shift pattern are enough for a scoped quote.

Request a Quote